Timeline

Spring 2010         Stakeholder Engagement initiated

Spring 2010         East Anglia Zonal Surveys and East Anglia ONE surveys commence

July 2010             Offshore windfarm Scoping Report submitted to IPC

July 2010             First Public Exhibition events held

Oct 2010              Supplementary Scoping Report (Electricity Works) submitted to IPC

Jan 2011              Formal Scoping Opinion received from IPC

April 2011            Statement of Community Consultation Published (SoCC)

April 2011            Second Public Exhibition events held

July 2011             Electricity Transmission Works Scoping Report submitted to IPC

July 2011             Third Public Exhibition events held (phase 1 consultation under the SOCC)

Jan 2012              Preliminary Environmental Information report published (Section 42 consultation)

Jan 2012              Phase 2 consultation under the SOCC

Nov 2012             Application for Consent submitted to IPC

2014                    Consent Application Decision

2015                    Construction on East Anglia ONE begins

2018                    East Anglia ONE construction completed