Timeline
Spring 2010 Stakeholder Engagement initiated
Spring 2010 East Anglia Zonal Surveys and East Anglia ONE surveys commence
July 2010 Offshore windfarm Scoping Report submitted to IPC
July 2010 First Public Exhibition events held
Oct 2010 Supplementary Scoping Report (Electricity Works) submitted to IPC
Jan 2011 Formal Scoping Opinion received from IPC
April 2011 Statement of Community Consultation Published (SoCC)
April 2011 Second Public Exhibition events held
July 2011 Electricity Transmission Works Scoping Report submitted to IPC
July 2011 Third Public Exhibition events held (phase 1 consultation under the SOCC)
Jan 2012 Preliminary Environmental Information report published (Section 42 consultation)
Jan 2012 Phase 2 consultation under the SOCC
Nov 2012 Application for Consent submitted to IPC
2014 Consent Application Decision
2015 Construction on East Anglia ONE begins
2018 East Anglia ONE construction completed